A full-scale, seven-unit multifamily renovation driven by a strategic plan

REBLD walked the building and advised on the construction strategy and cost before the client made the investment. What followed was a strategic plan that aligned with leasing goals: for REBLD to deliver the first model unit by March 8. The result? All seven units rented by May 1 — at full asking price.

The Project

REBLD converted this historic three-flat near Chicago’s lakefront into seven units in less than seven months, allowing the building to be fully-leased up prior to completion of construction. Fully-gutting the existing condition down to the brick, the team breathed new life in to this early 1900s building with custom condo-quality finishes, all new mechanicals, windows, roof, porch and an added garage roof deck. The result is a stunning upgrade to the building that continues to pay respect to its historical details by incorporating design elements like custom curved windows, original clay tile roofing, and renovation of the original portico.

Unique Aspects

  • Existing three-unit converted to seven

  • Curved custom windows

  • Third-floor penthouse with custom kitchen and mechanically-operated skylights

  • Garage re-build with custom roof deck

  • Custom landscaping with dog park

  • Custom bike rack

Challenges

  • Single point of entry to six of seven units

  • Finishing units to market prior to completion of construction

  • Aggressive schedule

Project Type

Full gut with condo-quality finishes

Location

East Andersonville

Units

7

Duration

7 Months

Cost

$2,000,000 ($300k-$305k/door)

Completed Project

Process

See more of our work

A mixed-use redevelopment of the former Real World house

REBLD transformed the former MTV Real World House in Wicker Park into eight luxury rental apartments with a brand new commercial space at ground level.

Location

Wicker Park

Project Type

Mixed-use full gut

Duration

8 months

A full gut transformation of a dead basement into a beautiful 2 bedroom unit

As part of Chicago's expanding ADU program, REBLD relocated mechanicals, created new masonry openings, and coordinated heavy excavation and structural upgrades in an occupied building to turn a dead basement into a habitable 8th unit with modern amenities.

Location

Edgewater

Project Type

Full ADU build-out and 3 bathroom/kitchen upgrades

Duration

5 months

Ready to REBLD?
Get in touch.

Ready to REBLD?
Get in touch.

Ready to REBLD?
Get in touch.